The script's 160-minute wait is timed from the cache warm leg's start, and the leg starts only after gate / select legs and a free runner. The job's 200-minute timeout left 40 minutes for that; a push to main on 2026-11-28 took 44 minutes from the run's start to the leg's start. A later start ended the job with a timeout instead of the script's error. The script now fails with its own error when the leg has not started 120 minutes after the script started, and the job's timeout is 290 minutes, longer than the start wait and the 160-minute save wait together. A test reads both timeouts from ci.yml and checks them against the script's limits.